Revised Road Work Schedule 6/18-6/22
***UPDATED REVISION***
Revision to the revision:
Paving will commence during the day on Monday June 18, 2018 9am to 4pm, mon – fri
Only the loop work will be occurring at night 8pm – 6am. Mon – thurs.
Week of 6/24-6/29
Loops will continue sun – thurs 8pm-6am
Any remaining milling & paving, shoulder backup, gutter work will be mon-fri 9am – 4pm.
***Revised Schedule 6/18-6/22***
The milling and paving will continue Monday night on the shoulders WB 8PM-6AM, then will resume during the daytime T-F, 9Am-4PM, with any remaining shoulder & side street work.
Loop work will begin on Monday night and continue nightly until complete. Approximately 2-3 weeks. Schedule will be S-F, 8pm-6am and will be at signalized intersections. Work will progress one intersection at a time.
All work is weather dependent and will shift accordingly.
****Schedule 6/25-6/29 ****
Any remaining gutter work, shoulder backup & cleanup will continue daytime with the hours of 9am-4pm, M-F
Loops will continue 8pm-6am S-F.
All work is weather dependent and will shift accordingly
Thank you.